Engineering guide

Software migration

Software migration moves an application, its data, its platform or the tooling that ships it to a new home while people keep using it. Done safely, it runs in waves, and no wave cuts over until the same gate checks pass.

  1. Assess A strategy and a wave per workload

  2. Pilot wave Simple workloads, non-production first

  3. Wave 1 Workloads grouped by dependency

  4. Wave 2 Same steps, more workloads

  5. Wave 3 Critical systems, once the pattern holds

  • Prepare and sync
  • Verify, old system on standby
  • Decommission

Plan gate after assessment

Switch-off gate before decommissioning

  • No traffic reaches the old system
  • Data archived, backups moved
  • Nobody needs the way back
Illustration: a wave plan. Waves repeat the same steps and overlap: one prepares while the one before it verifies.

What does software migration cover?

Four kinds of work share the name, and most projects mix two or more. Applications move to another data center, region, account or cloud, and a cloud move starts with a landing zone. Data is the one part you cannot redeploy. Platforms, from an operating system version to a database engine, are often upgraded in place across a fleet. And every other migration ships through the fourth kind: CI/CD and tooling.

Plan gate: a strategy per workload

Which migration strategy fits each workload?

AWS Prescriptive Guidance names seven migration strategies, the 7 Rs. Microsoft's Cloud Adoption Framework names eight, mostly the same. Both decide per workload, as does On-Premise vs. Cloud: The Major Differences (And Why It's Now a Per-Workload Decision). Ask in order and stop at the first yes.

  1. Is it unused, or worth less than the move?

    AWS reads no inbound connections for 90 days as a sign.

    YesRetire

  2. Does it have to stay where it is for now?

    Data residency, hardware with no cloud equivalent, a recent upgrade, or a dependency that must move first.

    YesRetain

  3. Would an off-the-shelf product do the job?

    Its data, sign-in and network connections still have to move.

    YesRepurchaseMicrosoft: Replace

  4. Is it healthy, and can it run unchanged on the target?

    Microsoft's advice: don't rehost problematic workloads, because the move does not fix them.

    YesRehostRelocate, for a whole platform at once

  5. Would a managed service or newer runtime save real work, with small code changes?

    AWS's example: SQL Server to Amazon RDS for SQL Server.

    YesReplatform

  6. Otherwise: is the architecture itself the blocker?

    The costliest path. For large migrations, AWS advises moving first and modernizing after.

    YesRefactor or re-architectMicrosoft: Refactor, Rearchitect or Rebuild

Where no answer is clear, look closer before the workload gets a wave. Google suggests a proof of concept.

Big bang or phased: how do you cut over?

The cutover is the moment the new system becomes the one that counts. Google's guidance is to avoid a zero-downtime requirement where the business can live without one, since it takes redundancy for every workload.

Cutover approaches compared
ApproachHow it worksRiskThe way backFits
Big bang Stop writes, move everything, switch in one window: the stop-the-world cutover in the legacy displacement patterns. HighOne missed dependency hits everything. Switch back, if no writes have landed on the new side. Small systems with a maintenance window.
Phased waves Groups of workloads move one at a time, each with its own cutover. MediumContained to one wave, while old and new are linked. Per wave. Earlier waves stay where they are. Large estates and fleets.
Parallel run Both process the same inputs, and outputs are compared until they match. Then you switch. LowCostly: two systems to run. The old system stays the record until the switch. Calculations, billing, reports.
Strangler fig New code grows around the old and takes over one capability at a time, behind a routing seam. LowPer step, plus transitional code to remove later. Route that capability back to the old code. Replacing a large legacy application.
Illustration: each line is the new system's share of live traffic over time. Dashed: shadow traffic, compared but not served.

Cutover gate: verified data, tested rollback, rehearsed cutover

How do you plan a rollback?

Decide before the night what counts as failure, who calls it, by when, and what happens to data written in between. Microsoft asks for rollback triggers such as error rates, a tested procedure and named rollback authority. Google adds a maximum time per step: when it runs out, the team rolls back.

The safe pattern for the data copies early, keeps the copy in sync and makes the final switch short: stop writes, wait until replication lag is zero, then compare checksums, not just row counts. Before the night, rehearse the whole runbook on production-sized data and time every step. Microsoft calls this a mock cutover or dress rehearsal.

Past the last row, the way back means syncing new writes in reverse, and Disaster Recovery in 2026: RTO vs RPO, the Four DR Strategies, and What EU DORA Requires notes that failing back is usually the harder half, because data has to be resynchronized.

Example cutover runbook
WhenStepWay back
Week beforeChange freeze: pipelines block releases to the source.Nothing to undo
Day beforeLast rehearsal on production-sized data, every step timed.Move the date
00:00Go or no-go: gate checks green, rollback owner named.Stop here
00:05Writes stopped; the source goes read-only.Reopen the source
00:25Lag at zero, final sync, checksums match.Discard the target, reopen the source
00:45DNS and load balancer point at the target; smoke tests pass.Point them back
01:00Writes open on the target. Rollback deadline.Replay new writes to the source, or fix forward
Illustration: an example cutover runbook. Your times come from the rehearsal.

What changes when a migration runs as a pipeline?

A fleet upgrade is one change applied hundreds of times. By hand, the batch stays as small as people can watch.

At Nike, Windows server upgrades for 900+ retail stores ran by hand across five teams until es.nl consolidated them into one self-service upgrade pipeline. Each server then took about 3 hours instead of 6 to 8, and 8 ran safely in parallel instead of 2. AWS frames wave size as how much parallel change you can tolerate. The pipeline raised that number.

At ASML, es.nl initiated offloading selected production machine tests to Google Cloud Platform, to increase throughput and shorten feedback cycles. Selected is the point: a first wave goes where the gain is clear.

Read the Nike caseRead the ASML case

By hand 2 servers at a time, 6 to 8 hours each

One pipeline 8 servers at a time, about 3 hours each

Illustration: one batch of upgrades on an 8-hour axis. Each bar is a server.

Where to start

Know your release path before the first wave

Every cutover ships through the same pipelines, approvals and handoffs as an ordinary release. The free Release Check shows what releases cost a year across your applications and where they wait. It takes under 5 minutes, with no call.